Milestones
- this mark was supplied by your project mentor
Project Management
Quizzes
- each quizz was self-marked based on the marking scheme
discussed in the lecture
Documents
- Stakeholder Interviews (2)
- included all relevant stakeholders
- detailed report of each stakeholder's requirements
- WBS & Risk Analysis (6)
WBS is:
- reasonably complete & detailed
- hierarchical
- breakdowns are exhaustive and non-overlapping
Risk Anlysis Includes:
- a reasonable number of likely risks
- impact and probability for each one
- mitigation strategy for high-score risks
Gantt Chart (3)
- includes all items in the WBS
- includes dependencies (predecessors)
- reasonable durations & end date
Achievement
- based on marking scheme agreed to for each project
Final Report
- detailed enough for another student to duplicate the project
- demonstrates good understanding of project's technical
aspects (e.g. no factual mistakes)